Automatic Fire Detection & Suppression Systems
S/N |
Activity |
IOCL Scope |
PROAID Scope |
1. |
Issue & shifting of supplied materials from stores to site |
✓ |
|
2. |
Assembling pump station at site |
|
✓ |
3. |
Installation of distributor blocks (Master & Secondary) |
|
✓ |
4. |
Welding of base block with frame of distributor blocks |
✓ |
|
5. |
Pipe laying, bending and installation from pump to distributor blocks |
|
✓ |
6. |
Welding of pipe clamp |
✓ |
|
7. |
Installation of Control Panel |
|
✓ |
8. |
Welding of Bracket of control panel with the structure |
✓ |
|
9. |
Flushing of pipe line with grease |
|
✓ |
10. |
Commissioning of entire system |
|
✓ |
11. |
Training of man power at site |
|
✓ |
Note: Anything not covered in the scope of supply of order will be in client's scope. Necessary gate pass, permit, scaffolding, welding, gas cutting if required will be in IOCL Scope |